We see that at the Sprint Planning meeting team committed to delivering 32 story points (SPs). This metric reflects the total scope added to the sprint before hitting “Start Sprint” button on Jira Scrum board.

Final commitment

"Final commitment" metric reflects any changes to an active sprint's scope , which - it means that if any work was added, removed, or an issue's estimate was changed after sprint’s start event, then this these changes would be reflected in Final commitment.
The final commitment is 36 SPs which is more than a team committed to at Sprint Planning (32 SPs). The chart (Estimation change metric) shows that this happened because the work estimate has increased.
By checking details about sprint issues (click anywhere on the area of Sprint 1), we find out that user stories' #4 and #6 estimate has been increased by 2 SPs each:

...