Added work

Added work

Definition

Issues that were added to the sprint after it started.

Category

Scope changes.

Formulas:

  • Final commitment = Initial commitment + Added work + Estimation change – Removed work

  • Total scope change = Added work + Estimation change – Removed work

In Sprint 4, the added work represents 13.19% relative to the Final Commitment. Along with estimation changes and removed work, it contributed to a total scope change of 19.78%.

You can see the detailed breakdown below the chart by clicking any interval on the chart.