Removed work

Removed work

Definition

Issues that were removed from the sprint after it started.

Category

Scope changes.

Formulas:

  • Final commitment = Initial commitment + Added work + Estimation change – Removed work

  • Total scope change = Added work + Estimation change – Removed work

In Sprint 3, the removed work represents 7.5% relative to the Final Commitment, whereas the added work is 13.75%. Along with estimation changes, the two metrics contributed to a total scope change of 26.25%.

You can see the detailed breakdown below the chart by clicking any interval on the chart.