Removed work
Definition
Issues that were removed from the sprint after it started.
Category
Scope changes.
Formulas:
Final commitment = Initial commitment + Added work + Estimation change – Removed workTotal scope change = Added work + Estimation change – Removed work
In Sprint 3, the removed work represents 7.5% relative to the Final Commitment, whereas the added work is 13.75%. Along with estimation changes, the two metrics contributed to a total scope change of 26.25%.
You can see the detailed breakdown below the chart by clicking any interval on the chart.