Agile Reports operates with data stored in Jira and stores only gadget-specific configuration. Thus, the migration from Server/DC to Cloud is a two-step process.

Step 1

Migrate Jira data such as projects, dashboards, issues, users, etc... from Server/DC to Cloud. Atlassian recommends using JCMA (Jira Cloud Migration Assistant | Atlassian Marketplace) for this.

Step 2

Once the Jira data is in Cloud the Agile Reports gadget’s configuration can be migrated. To do this we recommend using configuration export-import functionality. Follow these steps to migrate specific gadgets from Server/DC to Cloud:

  1. Open the gadget you want to migrate in Jira Server/DC and click “Export” → “Export settings”:

  2. Create the new gadget in Jira Cloud, navigate to “Import settings”, and upload the exported file:

  3. Note, that there is validation logic that checks whether all Jira data specified in exported configuration exists (for example on the screenshot the board with id “417” does not exist, because after migration the board may have changed its id):

  4. To continue click ”Import” and the configuration will be imported stating that the board was not found:

  5. Hence a specific piece of data (board id in our case) was not resolved the gadget will invite to specify it:


Note:
We recommend updating the Agile Reports and Gadgets Server/DC app to the latest version before migrating.