Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Duration: This option only calculates the actual working time when the issue was in "In Progress," excluding weekends, holidays, breaks, and non-working hours which you can setup in the Work schedule. In the same example, from Wednesday to the following Thursday, the Cycle Time would be 6 working days, as Saturday and Sunday are excluded.

Panel
panelIconId1f4a1
panelIcon:bulb:
panelIconText💡
bgColor#FFFFFF

Set the Work Schedule during the Calculation method selection ensures that time-based metrics accurately reflect either calendar days or actual working hours, including breaks and holidays. It helps avoid misleading results.