Commitment
Initial
The metric reflects the amount of work in Sprint before it started.
Final
The metric reflects the amount of work in Sprint after Sprint is finished.
If the Sprint is not finished, the metric reflects the current situation.
Final commitment = Initial commitment + Added work + Estimation Changed - Removed work.
Changes in work
Added
The metric reflects the amount of work added to Sprint before it is finished.
If the Sprint is not finished, the metric reflects the current situation.
Removed
The metric reflects the amount of work removed from the Sprint before it is finished.
If the Sprint is not finished, the metric reflects the current situation.
Re-estimated
The metric reflects the difference between estimation before the Sprint started and after the Sprint was finished.
If the issue was added during the sprint, it calculates as added work, even if their estimation was changed.
If the Sprint is not finished, the metric reflects the current situation.
Completion
The issue is completed if it has a status from the Done category and is in the last column of the Scrum Board to which it belongs.
You can set a custom Done status to manage Completion metrics.
Not completed work
The metric reflects the work not completed as a snapshot at Sprint’s end.
If the Sprint is not finished, the metric reflects the current situation.
Not completed work = Final Commitment - Completed work (final).
Completed work (Initial)
The metric reflects the amount of work planned before Sprint started and completed as a snapshot at Sprint’s end.
If the Sprint is not finished, the metric reflects the current situation.
Completed work (initial) = Completed work (final) - Completed Added work.
Completed work
The metric reflects the final scope work completed as a snapshot at Sprint’s end.
If the Sprint is not finished, the metric reflects the current situation.
Completed work (final) = Final commitment - Not completed.